Sl. No | Project | Cost | Capacity (MMTPA) |
(In Cr.) | |||
JLN Port Trust | |||
1 | Development of Container Terminals of 2000 Mtrs Length at JNPT (4th Container terminal) | 7915.00 | 60.00 |
Kamrajar Port Ltd. (Ennore) | |||
2 | Modification of existing Iron Ore Terminal to also handle coal (SIOTL) | 229.00 | 12.00 |
3 | Development of Marine Liquid Terminal -II on DBFOT Basis | 393.00 | 3.00 |
4 | Development of LNG Terminal on Captive basis | 5151.00 | 5.00 |
5 | Development of IOCL Oil Jetty (Captive) | 480.00 | 3.00 |
6 | Construction of Coal Berth 3 for TANGEDCO (Captive) | 235.14 | 9.00 |
7 | Construction of Coal Berth 4 for TANGEDCO (Captive) | 244.51 | 9.00 |
Deendayal Port Trust | |||
8 | Development of Oil Jetty to handle liquid cargo ship bunkering Terminal | 233.50 | 3.39 |
9 | Development of Marine Liquid Terminal Facilities consisting of SPM & Two product jetties in KPT waters at OOT,Vadinar on captive use basis | 448.00 | 24.50 |
Kolkata Port Trust | |||
10 | Setting up of Liquid Cargo Handling Jetty at Shalukkhali, Haldia Dock -II | 172.52 | 2.43 |
Mormugao Port Trust | |||
11 | Redevelopment of Berths 8, 9, and Barge Berths | 1145.36 | 19.22 |
New Mangalore Port Trust | |||
12 | Provide Handling Equipment at Berth No. 18 (Old berth no.12) for Handling Bulk Cargo & Containers under PPP Mode | 469.46 | 6.73 |
13 | Mechanization of Berth No. 14 for handling Container and other clean cargo on PPP mode | 280.71 | 6.02 |
Paradip Port Trust | |||
14 | Development New Coal Berth for handling of Coal imports at Paradip Port on BOT basis. | 655.56 | 10.00 |
15 | Development of Clean Multi-cargo Berth in Southern Dock | 430.78 | 5.00 |
16 | Development of Deep Draft Iron Ore berth. | 740.19 | 10.00 |
17 | Mechanisation of EQ1 to EQ3 berths | 1437.76 | 30.00 |
Visakhapatnam Port Trust | |||
18 | Development of East Quay-1A (EQ-1A) berth on south side of EQ-1 berth in the Inner harbour of Visakhapatnam Port on DBFOT basis | 313.39 | 7.36 |
19 | Extension of existing container terminal | 633.11 | 0.54 MTEUs |
VOC Port Trust, Tuticorin | |||
20 | Construction of North Cargo Berth-II | 332.16 | 7.00 |
21 | Development of Shallow draught Berth on PPP mode for handling construction materials | 65.37 | 2.00 |
22 | Development of facilities for Handling Thermal Coal for SPIC Electric Power Corpn Pvt Ltd (SEPC) | 214.50 | 2.50 |
Mumbai Port Trust | |||
23 | Bunkering Terminal | 50.00 | 2.00 |
PPP
Sl. No | Project | Cost | Capacity (MMTPA) |
(In Cr.) | |||
Chennai Port Trust | |||
1 | Container Terminal -1 M/s.CCTPL | 790.60 | 31.30 |
2 | Development of 2nd Container Terminal (M/s.CITPL) | 783.32 | 29.50 |
Cochin Port Trust | |||
3 | Vallarpadam Container Terminal ICTT | 2118.00 | 40.00 |
4 | LNG Terminal | 4182.00 | 5.00 |
5 | Crude Oil Handling Facility for BPCL-Kochi Refinery (Formerly KRL - a Central PSU) (Captive) | 720.00 | 13.00 |
JLN Port Trust | |||
6 | Container Terminal, NSICT | 750.00 | 13.20 |
7 | Extension of container berth by 330 m towards north | 600.00 | 10.00 |
8 | Third Container Terminal | 1078.00 | 15.60 |
9 | BPCL Jetty (Captive) | 200.00 | 5.50 |
Kamrajar Port Ltd. (Ennore) | |||
10 | Development of Marine Liquid Terminal - I on DBFOT Basis | 252.00 | 3.00 |
11 | Development of Coal terminal for users other than TNEB on BOT basis | 399.00 | 8.00 |
12 | Development of Container Terminal on DBFOT basis (2 phases) (Ph-1- Rs.724 Cr and Ph-2- Rs.546 Cr) | 1270.00 | 16.80 |
13 | Development of Multi Cargo berth on DBFOT Basis | 151.00 | 2.00 |
14 | Coal Berth-1 for TANGEDCO (Captive) | 80.38 | 8.00 |
15 | Coal Berth-2 for TANGEDCO (Captive) | 8.00 | |
Deendayal Port Trust | |||
16 | Development of 13th Berth other than liquid and container cargo berth | 188.87 | 1.50 |
17 | Development of 15th multipurpose cargo berth at Kandla | 188.87 | 1.50 |
18 | Container Freight Station | 41.07 | 3.00 |
19 | Dry Bulk Terminal off Terka near Tuna on BOT basis (Outside Kandla Creek) | 1060.00 | 14.11 |
20 | Development, operation & maintenance of Container Terminal (Berth 11&12) on BOT | 159.81 | 7.20 |
21 | Oil Jetty for IOCL (Captive) | 20.70 | 2.00 |
22 | Oil Jetty related facilities at Vadinar(ESSAR) (Captive) | 750.00 | 13.50 |
23 | Fifth Oil Jetty (IFFCO)(Captive) | 24.00 | 2.00 |
24 | Setting up of Captive Barge Jetty at Old Kandla (IFFCO) | 27.00 | 1.50 |
Kolkata Port Trust | |||
25 | Multipurpose Berth No. 12 | 35.00 | 1.12 |
26 | Multipurpose Berth No. 4A | 150.00 | 2.00 |
Mormugao Port Trust | |||
27 | Development of Coal Handling Terminal at Berth No.-7 | 406.00 | 4.61 |
28 | Bulk Cargo berths No. 5A & 6A | 250.00 | 5.00 |
New Mangalore Port Trust | |||
29 | Setting up of Bulk Cement Handling facility for M/s Ambuja Cement Ltd. (captive) | 98.00 | 1.00 |
30 | Construction of Captive Jetty for handling Coal by M/s. UPCL | 376.52 | 5.40 |
Paradip Port Trust | |||
31 | Mechanisation of Cargo Handling Project-1 | 37.32 | 2.00 |
32 | Mechanisation of Cargo Handling Project-2 | 25.13 | 2.00 |
33 | Supply, installation of 3 Nos. Of 100 tonne HMC. 1) By OSL 2) By Bothra Shipping Services 3) By ABCT Pvt. Ltd. | 87.75 | 3.75 |
34 | Supply, installation of 3 Nos. of HMC 1) By Crew Pvt. Ltd.(60T) 2) By OSL(100 T) 3) By OSL(60 T) | 87.75 | 3.25 |
35 | Captive Fertilizer Berth to PPL | 20.00 | 4.00 |
36 | Captive Fertilizer Berth to IFFCO | 26.17 | 4.00 |
37 | Construction of SPM Captive Berth | 500.00 | 15.00 |
38 | Mechanization of Central Quay-III Berth | 40.00 | 6.00 |
39 | Construction of 2nd SPM Captive Berth | 746.17 | 11.00 |
40 | Construction of 3rd SPM Captive Berth | 746.17 | 11.00 |
41 | Development of South Oil Jetty (Captive) | 222.29 | 10.00 |
Visakhapatnam Port Trust | |||
42 | Multipurpose Berths-EQ-8 & EQ-9 | 327.30 | 6.43 |
43 | Container Terminal, Outer harbour | 86.35 | 5.60 |
44 | Development of WQ-6 berth for handling Dry Bulk Cargoes | 114.50 | 2.08 |
45 | Development of EQ-10 berth for handling Liquid Cargoes | 55.38 | 1.84 |
46 | Mechanized Coal handling facilities at GCB in the Outer Harbour | 444.10 | 10.18 |
47 | Development of EQ-1 Berth | 323.18 | 6.41 |
48 | Upgradation of existing facility in the outer harbor and creation of new facility in the inner harbor for handling Iron ore. | 845.41 | 23.00 |
49 | Single Point Mooring –Captive facility developed by H.P.C.L | 643.48 | 8.00 |
VOC Port Trust, Tuticorin | |||
50 | Development of 7th Berth as Container Terminal | 135.00 | 5.00 |
51 | Berth No. 8 Container Terminal | 312.32 | 7.20 |
52 | Deployment of one number additional Harbour Mobile Crane at III & IV | 24.60 | 4.36 |
53 | Upgardation of Mechanical handling equipments in Berth No.1 to Berth No.6 and Beth No. 9 | 49.20 | 8.72 |
54 | NTPL Captive berth- North Cargo Berth I (Captive) | 43.72 | 6.30 |
55 | Coal Jetty-I & II | - | 6.25 |